Solution
Our team was engaged by Global Switch to provide project management, procurement and tendering support for a new High Voltage (HV) power supply from Ausgrid's Pyrmont Substation, to their facility in Darling Harbour. The project included the following deliverables:
- Development of specifications for ASP3 design consultants
- Client-side management of the design process overseeing the ASP3 designer
- Interface management with Ausgrid, including commercial negotiation
- Preparation of technical, contract and tendering documentation for the construction phase of the works
- Evaluation of tender submissions
- Commercial negotiations and contract award
Client
Global Switch
Sector
Power
Division
Project Services Group
Year
2014 - Ongoing