Solution
The CPB Samsung John Holland JV & CPB Dragados Samsung JV engaged ARCH Artifex to assist in two critical aspects of the project;
Procurement Advice
Our team undertook an independent due diligence review of the procurement of the tunnel ventilation system including axial fans, jet fans, dampers and attenuators. The review covered technical compliance, capacity and track record of suppliers as well as their ability to meet program commitments.
The key findings and recommendations provided the steering committee the confidence to proceed with significantly high-risk procurement packages.
Testing and Commissioning
The New M5 project had over 25,000 mechanical, electrical, ITS and control system assets that required testing and commissioning before handover to the operator and the subsequent opening.
A focus of this step was assisting in the planning for the following deliverables; Factory Acceptance Testing (FAT), Factory I Testing (FIT) and Site Acceptance Testing (SAT) and commissioning more than one-hundred (100) professionals and trade personal (at the peak of the project).
Client
CPB Samsung John Holland JV & CPB Dragados Samsung JV
Sector
Road
Division
Systems Engineering & Safety Assurance
Year
2016 - 2017
Next Project